Client: Samuel Ward Academy, Suffolk
Value: £75,000
Period on site: 4 weeks

  • Demolitions to merge existing washrooms
  • Formation of new open corridor access
  • Reconfiguration of under-slab drainage
  • New mechanical & electrical installation
  • Installation of 22no new WC compartments
  • Full height cubicle walls
  • Central island with wash troughs
  • New ceilings & flooring

We were delighted to work with one of our local secondary schools, Samuel Ward Academy in Haverhill, to offer a complete fixed price ‘turn key’ design and build installation.

Over four weeks around the school’s Christmas holidays, we completed a full refurbishment of washrooms.

The work included the demolition of the existing washrooms to increase space, a central island sink area and the installation of 22 new WC compartments.